On July 28th, the 1028-ton stainless steel ethylene distillation tower of Wanhua Yantai Industrial Park Phase II 1.2 million/year ethylene project, which was manufactured by Daming Heavy Industry, and the first tower of Fujian Industrial Park gasification project were delivered in advance at the same time, and a grand delivery ceremony was held.

Daming Manufacturing | Wanhua Chemical Torre de destilación de etileno y torre de gasificación de Fujian entregadas anticipadamente al mismo tiempo

Qian Zhaogang, Deputy General Director of Wanhua Chemical Engineering Construction Management Center and General Manager of Material and Equipment Department, Yang Fan, Deputy Director of Equipment Procurement of Material and Equipment Department of Wanhua Chemical, as well as Chen Ning, President of Daming Heavy Industry Group, Zhang Xiaolong, Financial Director of the Group, Shen Zhongyun, Director of Quality and Safety of the Group, Shao Xinghui, General Manager of Daming Process Equipment, Li Qianjin, Assistant to the General Manager of Daming Jingjiang Processing Center, and leaders of various functional departments of the Heavy Industry Group attended the ceremony.

Mr. Chen Ning, President of Daming Heavy Industry Group, expressed his warm welcome to the arrival of General Manager Qian Zhaogang and his party from Wanhua Chemical and thanked them for their long-term trust. He said that Wanhua Chemical is a core customer of Daming Heavy Industry, and the two sides have cooperated with each other for 94 sets of equipments in one year, with a total weight of about 7,000 tons. In the future, Daming Heavy Industry will continue to deliver each product with high quality and quantity and excellent performance according to the commitment of “two hundred percent”.

Wanhua Ethylene Distillation Tower Project Service Review

The 1.2 million/year ethylene project is the core of more than 20 projects in the second phase of Wanhua Yantai Industrial Park. Among them, the ethylene distillation tower equipment, as the largest stainless steel tower in Wanhua Yantai Industrial Park, is the core static equipment of the ethylene plant, with a diameter of 6.6 meters, a wall thickness of 46 mm, a length of 107 meters, and a weight of 1,028 tons.

Daming Manufacturing | Wanhua Chemical Torre de destilación de etileno y torre de gasificación de Fujian entregadas anticipadamente al mismo tiempo
default

Para completar la entrega con alta calidad y eficiencia, Daming Heavy Industry concedió gran importancia al proyecto de la torre de destilación desde el principio de la licitación, encargó la chapa de acero principal a la primera e hizo uso de la buena relación con la acería para garantizar que la chapa de acero llegara un mes antes de lo previsto.

During the manufacturing process, relying on the Group’s manufacturing integration advantages, coordinating with sister company Daming Jingjiang Processing Center to process the main plate on schedule, and giving full play to the processing strength of the unique domestic weld mechanical root clearing machine, which greatly shortened the weld clearing cycle and ensured the welding quality, and the welding qualification rate of the one-time film was as high as 99%.

The early delivery of this project is also inseparable from the day and night perseverance of all departments of Daming Heavy Industry, actively overcoming all kinds of difficulties, and boosting the smooth development of all the work, so that the project was completed 15 days ahead of schedule and reached the high quality requirements, which is of milestone significance for Daming Heavy Industry, and also marks that the overall equipment manufacturing capacity of Daming has been taken to a new level!